Week 8: 8/28 - 9/3

Summary of events:

Framing continued:
Door from laundry/mudroom to garage:
They didn't break thru the wall for security reasons, but they did cut out a small section so we could determine jamb depth for the fire-rated door that will go here:


More framing, fireplace opening:

new doorway into upstairs BR;
expanded upstairs BA:
The HVAC crew came this week and removed the old furnace:And the electrician worked on Saturday placing the blue electrical boxes:
Luckily, I just happened to be in the neighborhood dropping our daughter off at a playdate. I was able to go over the placement of the electrical boxes and have some moved to better locations.